    The Hyper-V host node CLE02VMN02 is reporting ECC drive errors in one of the RAID sub units. This is a critical event and cannot be deferred for future maintenance cycle due to potential of data loss and/or corruption that can result if additional drives fail. Our service team will be dispatched to the data center to perform RAID maintenance starting 9:00PM EST 2/3/2010.  All virtual servers hosted on this node will be offline for the duration of this maintenance window. We sincerely apologize for the inconvenience.

     We will post additional information regarding this event as it becomes available.

    • Post Points: 0
  • 02-03-2010 8:56 PM In reply to

    • skozyuk
    • Top 10 Contributor
    • Joined on 10-28-2007
    • Westlake, OH
    • Posts 328
    • Points 1,081

    Re: CLE02VMN02 Hyper-V Node Maintenance

    Virtual machines on CLE02VMN02 node will be taken offline shortly. Please follow this thread for updates.

    • Post Points: 0
  • 02-03-2010 11:22 PM In reply to

    • skozyuk
    • Top 10 Contributor
    • Joined on 10-28-2007
    • Westlake, OH
    • Posts 328
    • Points 1,081

    Re: CLE02VMN02 Hyper-V Node Maintenance

    The SAN volume scan is 36% through, hopefully it will pickup pace. 

    • Post Points: 0
  • 02-04-2010 12:48 AM In reply to

    • skozyuk
    • Top 10 Contributor
    • Joined on 10-28-2007
    • Westlake, OH
    • Posts 328
    • Points 1,081

    Re: CLE02VMN02 Hyper-V Node Maintenance

    Volume scan is currently 47% complete, we are going to let it run for several more hours.

    • Post Points: 0
  • 02-04-2010 2:30 AM In reply to

    • skozyuk
    • Top 10 Contributor
    • Joined on 10-28-2007
    • Westlake, OH
    • Posts 328
    • Points 1,081

    Re: CLE02VMN02 Hyper-V Node Maintenance

    Volume scan completed, restarting Hyper-V Guest servers

    • Post Points: 0
  • 02-04-2010 11:24 AM In reply to

    • skozyuk
    • Top 10 Contributor
    • Joined on 10-28-2007
    • Westlake, OH
    • Posts 328
    • Points 1,081

    Re: CLE02VMN02 Hyper-V Node Maintenance

    We have scheduled another maintenance window for Thursday, February 4th at 10:00PM EST. We will be replacing failed drive units in the SAN array servicing CLE02VMN02 Hyper-V node.

    • Post Points: 0
  • 02-04-2010 9:49 PM In reply to

    • skozyuk
    • Top 10 Contributor
    • Joined on 10-28-2007
    • Westlake, OH
    • Posts 328
    • Points 1,081

    Re: CLE02VMN02 Hyper-V Node Maintenance

    As a precaution we will shutdown all guest VMs serviced by this SAN unit and perform disk swap in powered down state. Please follow this thread for updates.

    • Post Points: 0
  • 02-04-2010 10:45 PM In reply to

    Re: CLE02VMN02 Hyper-V Node Maintenance

    I'm so frustrated. I don't even know you guys shut down the server today again as I didn't receive any email notice for each of your post. I just got the initial notice.

    when will be completed?

     Chris

    • Post Points: 0
  • 02-04-2010 11:36 PM In reply to

    • skozyuk
    • Top 10 Contributor
    • Joined on 10-28-2007
    • Westlake, OH
    • Posts 328
    • Points 1,081

    Re: CLE02VMN02 Hyper-V Node Maintenance

    SAN drive has been replaced and RAID volume reinitialized. We are currently restarting all Hyper-V guest servers.

    • Post Points: 0
  • 03-28-2010 8:22 AM In reply to

    • skozyuk
    • Top 10 Contributor
    • Joined on 10-28-2007
    • Westlake, OH
    • Posts 328
    • Points 1,081

    Re: CLE02VMN02 Hyper-V Node Maintenance

    We will be performing a driver and firmware upgrade today (Sunday, March 28th 2010 starting 10AM EST) on the 3Ware 9650 RAID controller as a follow-up measure. The new firmware release addresses number of issues we have experienced with this particular RAID controller during the last several months.

     As a precaution we have taken full backups of all data. The upgrade process should take approximately 15 to 20 minutes during which time we will have to reboot the server.
    • Post Points: 0
  • 03-28-2010 11:20 AM In reply to

    • skozyuk
    • Top 10 Contributor
    • Joined on 10-28-2007
    • Westlake, OH
    • Posts 328
    • Points 1,081

    Re: CLE02VMN02 Hyper-V Node Maintenance

     We will be shutting down guest VMs shortly, please follow this thread for updates.

    • Post Points: 0
  • 03-28-2010 12:50 PM In reply to

    • skozyuk
    • Top 10 Contributor
    • Joined on 10-28-2007
    • Westlake, OH
    • Posts 328
    • Points 1,081

    Re: CLE02VMN02 Hyper-V Node Maintenance

     Maintenance completed, all affected VMs are currently restarting.